The Problem
Jee was asked to carry out assurance for the potential future use of an isolation plug to facilitate the replacement of a topsides pig launcher valve on a major gas export pipeline in the North Sea.
In 2010, an isolation plug was used in the same pipeline to allow replacement of a section of pipework. It has been proposed that should isolation be required again, for example for a valve change-out, the same type of plug may be used. The client requested Jee to complete up-front technical assurance to ensure that using the same plug as in 2010 would be appropriate, taking into account any lessons learnt from the previous execution.
The Solution
Jee conducted a review of the 2010 operation and plug tool design to identify what further testing or clarifications should be sought during the engineering of any future operation using the same tool.
The scope of the assurance was to:
The Benefits
The assurance completed gave confidence to the client that the previous isolation tool used was suitable at that time and for re-use.
The recommendations for further work ensured that the overall risk associated with using the isolation tool in a future fast response scenario was minimised, ensuring that at that time focus would be on key areas of tool verification in the knowledge that other factors had already been assessed in advance.