The Scope
A major operator had identified the need to continue operation of an 18” condensate pipeline in the North Sea beyond its design life. The operator requested our team to conduct a lifetime extension (LTE) assessment to determine requirements for extending the design life of the pipeline.
The Solution
We completed an assessment of the permissible extension to operating life, utilising the methodology defined in NORSOK ISO/TS 12747 and Y-002. Our team progressed the assessment through the following stages:
During performance of the assessment, it became clear that the factor governing remnant life of the system was the potential for internal corrosion at the base of the inlet riser. Whilst inline inspection data was available for the majority of the system, quality of data in this region was compromised. To solve this issue, we performed a structural reliability assessment (SRA), utilising the remainder of inspection data to determine the acceptable remnant life.
The Benefits
From this assessment and recommendations, our client was given confidence that the pipeline was suitable for continued and safe operation over the coming years. In addition, they were clear on the actions required to manage integrity during the extended operating period and how to further increase the operating life if required. We have provided continued support to our client to ensure that the pipeline continues to operate safely and economically.